Software Development Contracts
This guide is based on UK law.
Overview
Where a business needs bespoke software solutions, the rights
and obligations of a software developer and of the business (the
software user), will be set out in a software development
contract.
There are two approaches to software development which can be
known as conventional and prototype approaches.
Under the conventional approach, there will be a detailed
specification of what the user requires from the outset. The
prototyping approach is more flexible. Although there will still be
a specification, it will be less detailed and the user requirements
are developed along the way, working with the developer.
This guide discusses the implications for the software
development contract arising out of these two rather different
approaches.
The contract differences will include those relating to the
software user's requirements, change controls, acceptance criteria,
project management and charges.
Requirements and change control
It is important to define the user's requirements in the
contract. For the conventional approach, this document may well be
a long, detailed and definitive statement. It may itself be the
subject of a separate contract.
Once the development work is under way, it is inevitable that
changes will be required. For a project of any complexity, the
software will rarely be implemented as originally specified. A
change control procedure will facilitate the steps of suggesting,
documenting, pricing and implementing variations, and this should
be set out in the contract.
However, where the requirements are not initially well-defined
and are being developed through prototyping, the objective for the
user can be stated only at a high level, by means of a short
concept statement or guide. This too should be identified in the
contract. As part of the iterative process, it will be interpreted
creatively by the supplier, with the active co-operation of the
user. It will be discussed and refined as the work progresses,
until both parties agree that the objective has been achieved.
Change control procedures are irrelevant because the process
assumes constant change.
Acceptance criteria
For conventional development there should always be acceptance
testing by the user. The user has to be sure that before final
payment, the system or software is performing according to its
requirements. Yet to define the tests themselves at the time the
contract is made is likely to be impossible. Nevertheless, the
formal procedure for acceptance, allowing for repeat testing, and
the deadline by which the tests should be completed, ought to be
set out in the contract. If the user does not carry out the testing
completely or uses the software operationally, then acceptance
should be deemed to have taken place, for the supplier to be
entitled to payment.
For prototyping, the process of acceptance is ongoing, and
implementation will take place when the user is satisfied that it
has a useful system which meets its objective.
Project management
It is essential for project management procedures to be agreed
and specified in the contract. Prototyping relies heavily on
effective project management, because the method of working allows
for uncertainty and encourages changes of direction, and this must
be managed. For traditional software development, lack of project
management is at the heart of many project failures. It is
therefore crucial for each party to establish agreed procedures for
management and review in the formal contract.
Charges
It is usually difficult to be aware of all the variables in
assessing costs accurately at the outset of development. Some
conventional development is carried out for a fixed price. As a
general principle this is inadvisable, and variations which arise
will probably be more highly priced than where the basis for
charging is on the time spent. It may be possible to place a cap on
the price. Suppliers tend to prefer this latter method, which gives
them more certainty for cash flow. This is the normal method of
charging used for prototyping contracts.
Estimated pricing is based on time costs, with a margin for
error. The supplier will alert the user if the estimated figure is
being approached, or if radical changes are made as the application
unfolds, causing significant cost increases. The user can then make
its decision about more or fewer resources or features and the
extent of functionality.