Facts
The Claimant company, Psychometric Services Limited ('PSL'),
provided psychometric testing services for companies to assess job
candidates. In 1999 PSL wanted to expand its services by
enabling candidates to complete its tests from a home computer via
the internet.
PSL approached Merant who quoted £195,000 to develop the
websites. Accordingly a contract was entered into on 20
October 1999 between the parties. Under the contract Merant's
fees were capped at £195,000. However, during the project the
parties agreed that the work required of Merant far exceeded that
which was originally anticipated. The parties therefore
signed a Variation Letter on 10 March 2000 removing the £195,000
cap. During the course of the project Merant received over
£700,000 from PSL. Merant claimed that PSL owed a further
£960,000.
PSL had secured three clients for its websites, notably
Stepstone. The Stepstone contract value was in excess of
£14m. PSL displayed the potential to be a market leader and
highly profitable. PSL's ability to fulfil this potential was
however impaired as its websites were not operating properly.
It was agreed between the parties that the software contained
defects and needed additional work to remedy these defects.
The number of and seriousness of these defects and their cause were
however disputed by the parties.
Although it was vital to PSL's business that these defects be
remedied quickly, PSL had lost faith in Merant's ability and wanted
to employ another software developer to further develop and perfect
the software. To do this PSL required the source code for the
software.
PSL had neither realisable assets nor spare funds. PSL was
reliant on its ability to use the websites if its business was to
survive. The parties agreed that the likely outcome of PSL
not receiving the source code would be that PSL would go into
liquidation.
PSL made an application for an interim injunction to compel
Merant to provide a copy of the source code. PSL claimed that
it had a contractual right to the source code. Merant denied
this and argued that PSL was attempting to obtain software which it
had ordered but not yet paid for. Merant further maintained
that retaining the source code was the only way in which PSL would
be persuaded to pay this outstanding sum.
PSL argued that the balance of convenience favoured the grant of
the relief sought. Merant denied this and relied on
Zockoll Group Ltd v Mercury Communications
Ltd [1998] FSR 354 (which cited Nottingham
Building Society v Eurodynamics Systems Plc
[1993] FSR 468) to support its contention that PSL had failed
to justify the drastic relief sort.
The relevant contractual clauses referred to by Laddie J were
the following:
'Work Product Defined as the
software deliverables and/or documentation developed hereunder and
delivered to Company under a Project Designation.
Ownership(a) Consultant hereby assigns to Company right, title and
interest in and to the Work Product delivered hereunder, except
with respect to any Consultant Intellectual Property (as defined
below).
The Consultant Intellectual Property was defined as intellectual
property developed by Merant prior to or independently of the
contract.
PSL will undertake that MERANT will be its sole supplier of web
development services for a period of 2 years from the date of
delivery of this project. … For absolute clarity, in the unlikely
event of PSL being dissatisfied with MERANT's work, payment of the
lesser of price of work performed or £195,000 plus VAT will
discharge PSL of this obligation to MERANT and PSL may then proceed
with an alternate supplier.'
MERANT will assign to PSL or its successors an irrevocable,
non-exclusive, world-wide royalty-free licence to use and
internally distribute copies of the source code and to prepare
derivative works based in all the licensed materials. The
licensed materials are for PSL's internal business use only and are
not authorised for repackaging, re-sale, or any other commercial
use or distribution.'
Judgment
Laddie J considered the merits of PSL's contractual right to the
source code. The Judge emphasised that it was not necessary
for him to reach a final conclusion on this issue. He did
however proceed to give his opinion on the merits of PSL's
contractual claim.
The Judge did not accept PSL's claim to be entitled to the
source code under the contractual provisions defining 'work
product' and 'ownership' of the work product. The term 'work
product' was defined as 'software deliverables', but 'software
deliverables' was undefined in the contract. According to the
Judge, in a normal software development context, "software
deliverables" would include the object code but not the source
code. Therefore the source code could only be called a
software deliverable if there was some other term in the contract
to provide a copy of the source code.
A clause which did strengthen PSL's contractual claim was the
clause defining 'Long Term Commitment'. Under this clause
Merant would be the sole supplier of web development services to
PSL for two years but if PSL were dissatisfied with Merant's work
and if PSL had paid £195,000 then it would be entitled to shorten
this period of two years and use an alternative supplier.
According to the Judge this clause would not make commercial sense
if PSL had satisfied the two conditions but were not entitled to
the source code, because, without the source code, no further
development would be possible.
The next clause considered was the clause defining 'Ownership of
Source Code'. In the Judge's opinion this clause strongly
supported PSL's contractual claim to the source code.
For the purposes of the application the Judge proceeded on the
basis that PSL's contractual claim to the source code was
arguable. The Judge then considered where the balance of
convenience lay.
As mentioned previously Merant referred the Judge to the
Zockoll case. However, the Judge was
not convinced that this case added much by way of guidance as the
relief sought in the present case amounted to nothing more than an
order for delivery up and contained none of the features which make
courts reluctant to grant such relief. The Zockoll
case did however emphasize the primary consideration of
finding the course which is likely to involve the least risk of
injustice following final judgment, as in all cases dealing with
interlocutory relief.
The Judge found that the least risk of injustice involved
granting the injunction and providing PSL with a copy of the source
code. The following factors weighed heavily in the Judge's
reasoning. If PSL were refused the source code it would
almost certainly go into liquidation. This would seriously
affect PSL, its employees, its backers and its customers. It
would be a significant injustice if, at trial, it was found that
PSL was entitled to the source code. Furthermore, in such
circumstances PSL's potential damages would be
unquantifiable. This had to be compared with Merant's
position. Merant had given notice of termination and was only
interested in recovering the outstanding £960,000. There was
no risk to employees or third parties. If after granting the
injunction it was found that PSL was not entitled to the source
code, this would not involve a significant injustice to
Merant. For Merant, the worst case scenario if PSL obtained
the source code was that Merant would not be paid, thus incurring a
loss of £960,000. If PSL were not given the source code it
would likely go into liquidation and Merant would not be paid, thus
again incurring a loss of £960,000. There would therefore be
no additional risk of loss for Merant if the injunction was
granted. In fact, the only way in which Merant would have any
chance of recovering these sums would be if PSL obtained the source
code, remained in business and hopefully acquired the resources to
meet any obligations owed to Merant. The Judge dismissed the
suggestion that PSL should provide any security to Merant as PSL
simply did not have the available resources to provide this.
Commentary
This case was decided in 2001 but was only reported more
recently. The Judge did not create new law in granting the
injunction. This case does however emphasize the importance
of issues concerning access to source code for both customer and
software developer.
Often, the parties will enter into an Escrow Agreement whereby a
copy of the source code will be deposited with a third party, and
the third party will release that copy to the customer on the
occurrence of a specified event or events. The most common
(and usually uncontroversial) example is the liquidation of the
supplier.
Far more controversial is the extent to which the customer
should have access to the source code if the parties fall into
dispute, for example about the quality of the supplier's
work. The customer may be heavily reliant on the system, as
PSL was, so that, without the source code, the customer's business
is badly damaged, ruined even. The supplier, on the other
hand, will recognise that his commercial leverage over the customer
is largely conditional on preventing the customer from having
access to the source code.
Where the parties are in dispute about the quality of the
supplier's work, resolving that dispute at a technical level is
often a drawn out process. Proceedings to trial may take more
than a year, which is plainly far too long for a customer like PSL
to wait, hence its application in these proceedings.
Of course, every case will turn on its facts, and an important
point in this case was the apparent strength of PSL's claim to a
contractual right to the source code. As the Judge said, this
is not usually the position. Given this, and the balance of
convenience between granting and refusing access to the source
code, it is not surprising that the Judge decided that PSL should
have access. Yet the case does raise some difficult issues
about how the financial standing of the parties will impact upon
the court's approach. The Judge considered that PSL's
perilous state made the reasons for granting the injunction all the
more compelling. In practical terms there is little doubting
the logic behind this, and the Judge seems to have concluded that
Merant's best chance of getting paid involved keeping PSL
alive. Yet, from Merant's point of view, this loss at the
interlocutory stage represents a very significant blow to its
commercial position. On the judge's reasoning, PSL may not
have been entitled to the source code had it been a more
substantial and financially robust organisation. This raises
difficult questions about the extent to which a party's financial
circumstances should be taken into account when determining
entitlement to relief.